Water is the ultimate enemy of soil compaction. When we are tasked with laying deep utility mains in areas with high water tables, the trench environment becomes a hostile swamp. Many novice contractors believe they can simply throw crushed stone into standing water and use a heavy vibratory plate compactor to beat it into submission. This demonstrates a complete misunderstanding of fluid dynamics.
Water is an incompressible fluid. If you run a heavy steel plate over a subbase that is fully saturated, the downward impact force has nowhere to go. Instead of compressing the soil, the energy transfers into the trapped water, forcing it violently upward. This is known on the grade as "pumping." The soil literally turns to jelly, rolling in waves beneath the machine, and the fine silts and binders are washed out of the aggregate, leaving a structurally compromised mess.
Before a gasoline, diesel, or electric plate ever touches the dirt, aggressive dewatering must occur. We utilize heavy-duty trash pumps and well-point systems to draw the water table down below the bottom of the excavation. Once the trench is dry, we typically backfill the bottom lift with "clear stone"—a clean, washed aggregate with no fine dust, usually 20 mm to 40 mm [approx. 3/4 to 1.5 inches] in size. Clear stone is self-compacting to a degree, allowing water to flow through it without washing away structural integrity. When I run a plate compactor over clear stone, I am simply vibrating the rocks into a tight matrix. The operator must be hyper-aware: if water begins to bleed to the surface under the vibration of the plate, you must stop immediately, let the trench drain, and reassess your dewatering strategy before you destroy the subgrade.